The Pool Building And Installation Process

Typically, most homeowners decide to install a swimming pool during a season when the weather is at its best. Feeling they have worn out their welcome in their neighbor’s pools or tired of traveling to a crowded beach, they have concluded that the best way to beat the heat is to install their own pool.

Having finalized the design and established the cost of the new swimming pool, the next matter on the mind of most homeowners is the length of time involved in pool building and installation. The time it takes to install a swimming pool will depend on various factors, these include:

Process of Planning

• New pool
• Pool type (above-ground, in-ground, fiberglass, concrete)
• Selection of site
• Weather conditions
• Building guidelines
• Number of contractors

Ensure that you ask the pool specialist about the timeframe during the designing process. It is crucial to have clear expectations of the duration of the design and installation process to prevent unnecessary delays and avoid disappointment.

Among the most time-consuming parts of the process is the design of the swimming pool. The design process will largely influence the end result and ensure that the end result will be to your liking. Uncomplicated pool designs could take two weeks or so to complete; however, for more complicated concrete pool designs and shapes, the process could take months.

The pool contractor will need working drawings and engineer plans, which will then be submitted for building approval from the council. A planning permit may be required, and this process could take up to 6 weeks to complete.

Concrete Pools

As can be expected, concrete pools will take a longer time to build compared to pre-fabricated above-ground or in-ground pools. Excavators will be brought in to dig a hole for your swimming pool before the framework, drainage layers, and plumbing are completed. Next, the spraying of concrete will be done and allowed to cure. The process could take from three to four weeks.

Before the final works can be done, the concrete must be cured. Following this, the tile installation, paving, coping, fencing, and other final details can be done. This phase could take between four and six weeks. As such, a concrete pool can be expected to be ready for use in 4 to 6 months.

Fiberglass Pools

These pools can be more quickly installed compared to concrete pools; however, the building approval process must be completed before construction starts. After the approval is granted, the process of installation can be fairly fast.

In-ground Fiberglass Pools

Typically, it takes anywhere from seven to ten days to build an in-ground fiberglass pool. If an in-ground, pre-fabricated pool is being installed, any rainfall could possibly slow down the construction process by as long as two weeks. This is because time would be needed for draining the pool.

Above-ground Pools

These pools can be installed within a day or two; however, for a more permanent structure, a deck and fencing around the pool will be needed.